December 31, 1998.
    Take notice that the following hydroelectric application has been 
filed with the Federal Energy Regulatory Commission and is available 
for public inspection.
    a. Type of Filing: Request for Extension of Time to Commence 
Project Construction.
    b. Applicant:  Summit Energy Storage, Inc.
    c. Project No.: The proposed Summit Pumped Storage Hydroelectric 
Project, FERC No. 9423-024 is to be located near Norton and Wadsworth, 
in Summit and Medina Counties, Ohio.
    d. Date Filed: November 17, 1998.
    e. Pursuant to: Public Law 104-243.
    f. Applicant Contact: Donald H. Clarke, Esq., Wilkinson, Barker, 
Knauer & Quinn, LLP, 2300 N Street, N.W., Suite 700, Washington, DC 
20037, (202) 783-4141.
    g. FERC Contact: Mr. Lynn R. Miles, (202) 219-2671.
    h. Comment Date: February 19, 1999.
    i. Description of the Request: The licensee requests that the 
deadline for commencement of construction for FERC Project No. 9423 be 
extended for three consecutive two-year Periods. The deadline to 
commence project construction for the project would be extended to 
April 11, 2001. The deadline for completion of construction would be 
extended to April 11, 2007.
    j. This notice also consist of the following standard paragraphs: 
B, C1, and D2.
    B. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of the Rules of Practice and Procedure, 18 CFR Part 385, 
subpart B. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    C1. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS,'' ``PROTEST'' or 
``MOTION TO INTERVENE,'' as applicable, and the project number of the 
particular application to which the filing is in response. Any of these 
documents must be filed by providing the original and 14 copies as 
required by the Commission's regulations to: The Secretary, Federal 
Energy Regulatory Commission, 888 First Street, N.E., Washington, D.C. 
20426. An additional copy must be sent to: The Director, Division of 
Project Compliance and Administration, Office of Hydropower Licensing, 
HL-21, at the above address. A copy of any comments, protest, or 
motions to intervene, must also be served upon the representative of 
the applicant specified in this notice.
    D2. Agency Comments--The Commission invites federal, state, and 
local agencies to file comments on the described application. (Agencies 
may obtain a copy of the application directly from the applicant. The 
application may be viewed on the web site at www.ferc.fed.us. Call 
(202) 208-2222 for assistance.) If an agency does not file comments 
within the time specified for filing comments, the Commission will 
presume that the agency has none. One copy of an agency's comments must 
also be sent to the applicant's representatives.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 99-160 Filed 1-5-99; 8:45 am]