DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission
[Docket No. CP99-164-000]


Panhandle Eastern Pipe Line Company; Notice of Request Under 
Blanket Authorization

January 27, 1999.
    Take notice that on January 19, 1999, Panhandle Eastern Pipe Line 
Company (Panhandle), P.O. Box 1642, Houston, Texas 77251-1642, filed in 
Docket No. CP99-164-000 a request pursuant to Sections 157.205 and 
157.211 of the Commission's Regulations under the Natural Gas Act (18 
CFR 157.205, 157.211) for authorization to construct, own and operate 
certain facilities to be located in Scott County, Illinois, in order to 
establish a new delivery point for Soyland Power Cooperative, Inc. 
(Soyland), under Panhandle's blanket certificate issued in Docket No. 
CP83-83-000, pursuant to Section 7 of the Natural Gas Act, all as more 
fully set forth in the request that is on file with the Commission and 
open to public inspection.
    Panhandle proposes to install two 10-inch hot taps, check valves 
and associated facilities on Panhandle's mainline facilities. Panhandle 
states that it will also install electronic gas measurement equipment 
on the proposed metering facilities to be constructed and installed by 
Soyland. Panhandle states that the proposed interconnection will be 
utilized to provide transportation service to Soyland and that the new 
interconnection will be designed to deliver up to 96,000 Dth/day of 
natural gas. Panhandle states that the estimated cost of the proposed 
facilities is approximately $252,000.
    Any person or the Commission's staff may, within 45 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to Section 157.205 of 
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
the request. If not protest is filed within the time allowed therefor, 
the proposed activity shall be deemed to be authorized effective the 
day after the time allowed for filing a protest. If a protest is filed 
and not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for

[[Page 5045]]

authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A Watson, Jr.,
Acting Secretary.
[FR Doc. 99-2367 Filed 2-1-99; 8:45 am]
BILLING CODE 6717-01-M