[Federal Register Volume 64, Number 81 (Wednesday, April 28, 1999)]
[Notices]
[Pages 22860-22861]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-10591]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Application Accepted for Filing and Soliciting 
Comments, Motions To Intervene, and Protests

April 22, 1999.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 11717-000.
    c. Date Filed: April 5, 1999.
    d. Applicant: Universal Electric Power Corporation.
    e. Name of Project: Mississinewa Lake Dam Hydroelectric Project.
    f. Location: On the Mississinewa River near the town of Peru, in 
Miami County, Indiana. The project would utilize the U.S. Army Corps of 
Engineers Mississinewa Lake Dam and reservoir.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. Secs. 791(a)-
825(r).
    h. Applicant Contact: Ronald S. Feltenberger, Universal Electric 
Power Corporation, 1145 Highbrook Street, Akron, Ohio 44301, (330) 535-
7115.
    i. FERC Contact: Tom Dean, [email protected], 202-219-2778.
    j. Deadline for filing comments, motions to intervene, and 
protests: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE, Washington, DC 20426.
    The Commission's Rules of Practice and Procedures require all 
intervenors filing documents with the Commission to serve a copy of the 
document on each person on the official service list for the project. 
Further, if an intervenor files comments or documents with the

[[Page 22861]]

Commission relating to the merits of an issue that affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. The project would be located at the existing U.S. Army Corps of 
Engineers Mississinewa Lake Dam and would consist of the following 
proposed facilities: (1) a 130-foot-long, 78-inch-diameter penstock; 
(2) a powerhouse on the tailrace side of the dam housing two turbine 
generating units with a total installed capacity of 3.0 MW; (3) a 800-
foot-long, 14.7 kV transmission line; and (4) other appurtenances.
    Applicant estimates that the average annual generation would be 
18,000 MWh and that the cost of the studies under the permit would be 
$1,000,000.
    l. A copy of the application is available for inspection and 
reproduction at the Commission's Public Reference Room, located at 888 
First Street, NE, Room 2A, Washington, DC 20426, or by calling (202) 
208-1371. This filing may be viewed on the web at http://
www.ferc.fed.us/online/rims.htm (call 202-208-2222 for assistance). A 
copy is also available for inspection and reproduction at the address 
in item h above.
    Preliminary Permit--Anyone desiring to file a competing application 
for preliminary permit for a proposed project must submit the competing 
application itself, or a notice of intent to file such an application, 
to the Commission on or before the specified comment date for the 
particular application (see 18 CFR 4.36). Submission of a timely notice 
of intent allows an interested person to file the competing preliminary 
permit application no later than 30 days after the specified comment 
date for the particular application. A competing preliminary permit 
application must conform with 18 CFR 4.32(a) and (b)(1).
    Preliminary Permit--Any qualified development applicant desiring to 
file a competing development application must submit to the Commission, 
on or before a specified comment date for the particular application, 
either a competing development application or a notice of intent to 
file such an application (see 18 CFR 4.36). Submission of a timely 
notice of intent to file a development application allows an interested 
person to file the competing application no later than 120 days after 
the specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.32(a), (b), and (c).
    Notice of Intent--A notice of intent must specify the exact name, 
business address, and telephone number of the prospective applicant, 
and must include an unequivocal statement of intent to submit, if such 
an application may be filed, either a preliminary permit application or 
a development application (specify which type of application). A notice 
of intent must be served on the applicant(s) named in this public 
notice.
    Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211 
and .214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    Filing and Service of Responsive Documents--Any filings must bear 
in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT TO 
FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', ``PROTEST'', 
``MOTION TO INTERVENE'', as applicable, and the Project Number of the 
particular application to which the filing refers. Any of the above-
named documents must be filed by providing the original and the number 
of copies provided by the Commission's regulations to: The Secretary 
and an additional copy must be sent to Director, Division of Project 
Review, at the above-mentioned address. A copy of any notice of intent, 
competing application or motion to intervene must also be served upon 
each representative of the Applicant specified in the particular 
application.
    Agency Comments--Federal, state, and local agencies are invited to 
file comments on the described application. A copy of the application 
may be obtained by agencies directly from the Applicant. If an agency 
does not file comments within the time specified for filing comments, 
it will be presumed to have no comments. One copy of an agency's 
comments must also be sent to the Applicant's representatives.
David P. Boergers,
Secretary.
[FR Doc. 99-10591 Filed 4-27-99; 8:45 am]
BILLING CODE 6717-01-M