[Federal Register Volume 64, Number 93 (Friday, May 14, 1999)]
[Notices]
[Pages 26390-26395]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-12239]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGUY

Federal Energy Regulatory Commission
[Docket No. EG99-127-000, et al.]


Foote Creek III, LLC, et al.; Electric Rate and Corporate 
Regulation Filings

May 6, 1999.
    Take notice that the following filings have been made with the 
Commission:

1. Foote Creek III, LLC

[Docket No. EG99-127-000]

    Take notice that on April 30, 1999, Foote Creek III, LLC, 1455 
Frazee Road, Suite 900, San Diego, California, 92108, filed with the 
Federal Energy Regulatory Commission an application for Commission 
determination of exempt wholesale generator status pursuant to Part 365 
of the Commission's Regulations.
    Foote Creek III, LLC, is a Delaware limited liability company that 
intends to construct, own and operate a 24.75 MW generation facility 
consisting of thirty-three (33) NEG Micon Model NM 750/44 wind turbine 
generators in Carbon County, Wyoming, Foote Creek III, LLC, is engaged 
directly and exclusively in the business of owning or operating, or 
both owning and operating, all or part of one or more eligible 
facilities and selling electric energy at wholesale.
    Comment date: May 27, 1999, in accordance with Standard Paragraph E 
at the end of this notice. The commission will limit its consideration 
of comments to those that concern the adequacy or accuracy of the 
application.

2. Western Systems Power Pool

[Docket No. ER91-195-037]

    Take notice that on April 30, 1999, the Western Systems Power Pool 
(WSPP) filed certain information as required by Ordering Paragraph (D) 
of the Commission's June 27, 1991 Order (55 FERC para. 61,495) and 
Ordering Paragraph (C) of the Commission's June 1, 1992 Order On 
Rehearing Denying Request Not To Submit Information, And Granting In 
Part And Denying In Part Privileged Treatment. Pursuant to 18 CFR 
385.211, WSPP has requested privileged treatment for some of the 
information filed consistent with the June 1, 1992 order. Copies of 
WSPP's informational filing are on file with the Commission, and the 
non-privileged portions are available for public inspection.
    Comment date: June 1, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

3. Morgan Stanley Capital Group Inc.

[Docket No. ER94-1384-023]

    Take notice that on April 29, 1999, the above-mentioned power 
marketer filed a quarterly report with the Commission in the above-
mentioned proceeding for information only. This filing is available for 
public inspection and copying in the Public Reference Room or on the 
web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

4. Citizens Power Sales; Enron Energy Services, Inc.; CL Power 
Sales Seven, L.L.C.; CL Power Sales Eight, L.L.C.; CL Power Sales 
Fourteen, L.L.C.; CL Power Sales One, L.L.C.; CL Power Sales Three, 
L.L.C.; CL Power Sales Four, L.L.C.; CL Power Sales Five, L.L.C.; 
CL Power Sales Ten, L.L.C.; Sonat Power Marketing L.P.; Sonat Power 
Marketing Inc.; PacifiCorp Power Marketing, Inc.; PSEG Energy 
Technologies Incorporated; Select Energy, Inc.; e prime, inc.; 
FirstEnergy Trading and Power, Marketing, Inc.; Southern Company 
Energy, Marketing L.P.; Enron Power Marketing, Inc.; Competitive 
Utility Services Corp.; DPL Energy; Edison Source; Entergy Power 
Marketing Corp.

[Docket Nos. ER94-1685-024; ER98-13-009; ER96-2652-028; ER96-2652-029; 
ER99-891-001; ER95-892-039; ER95-892-040; ER95-892-041; ER95-892-042; 
ER96-2652-027; ER96-2343-011; ER95-1050-017; ER95-1096-018; ER97-2176-
009; ER95-1269-014; ER99-14-003; ER95-1295-012; ER97-4166-004; ER94-24-
029; ER97-1932-009; ER96-2601-011; ER96-2150-013; ER95-1615-017]

    Take notice that on April 30, 1999, the above-mentioned power 
marketers filed quarterly reports with the Commission in the above-
mentioned proceedings for information only. These filings are available 
for public inspection and copying in the Public Reference Room or on 
the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

5. Duke Energy Marketing Corp.; Constellation Power Source, Inc.; 
NRG Power Marketing, Inc.; Pepco Services, Inc.; NESI Power 
Marketing, Inc.; DTE Energy Trading, Inc.; Alliance Power 
Marketing, Inc.; PG&E Power Service Company; Edison Mission 
Marketing & Trading, Inc.; Colonial Energy, Inc.; CL Power Sales 
Two, L.L.C.; CL Power Sales Six, L.L.C.

[Docket Nos. ER96-109-018; ER97-2261-009; ER97-4281-007; ER98-3096-003; 
ER97-841-003; ER97-3834-006; ER96-1818-013; ER94-1394-020; ER99-852-
002; ER97-1968-007; ER97-1968-008; ER95-892-038; ER96-2652-026]

    Take notice that on April 30, 1999, the above-mentioned power 
marketers filed quarterly reports with the Commission in the above-
mentioned proceedings for information only. These filings are available 
for public inspection and copying in the Public Reference Room or on 
the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

6. Strategic Energy Ltd.

[Docket No. ER96-3107-009]

    Take notice that on April 27, 1999, the above-mentioned power 
marketer filed a quarterly report with the Commission in the above-
mentioned proceeding for information only. This filing is available for 
public inspection and copying in the Public Reference Room or on the 
web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

7. Central Hudson Gas & Electric Corporation; Consolidated Edison 
Company of New York, Inc.; Long Island Lighting Company; New York 
State Electric & Gas Corporation; Niagara Mohawk Power Corp.; 
Orange & Rockland Utilities, Inc.; Rochester Gas & Electric Corp.; 
Power Authority of the State of New York; New York Power Pool

[Docket No. ER97-1523-004, OA97-470-005, and ER97-4234-003 (not 
consolidated)]

    Take notice that on April 30, 1999, the Member Systems of the New 
York Power Pool (Member Systems), tendered for filing a revised 
Independent System Operator Open Access Transmission Tariff (ISO OATT), 
a Market Administration and Control Area Services Tariff (ISO Services 
Tariff), a revised Independent System Operator Agreement (ISO 
Agreement), a revised New York State Reliability Council Agreement 
(NYSRC Agreement), a revised Agreement between the Independent System 
Operator and

[[Page 26391]]

Transmission Owners (ISO/TO Agreement) and a revised Agreement between 
the Independent System Operator and the New York State Reliability 
Council (ISO/NYSRC Agreement).
    The Member Systems state that this filing was made in compliance 
with the Commission's orders dated June 30, 1998 and January 27, 1999. 
See Central Hudson Gas & Electric Corp., et al., 83 FERC para. 61,352 
(1998), 86 FERC para. 61,062 (1999).
    A copy of this filing was served upon all persons on the 
Commission's official service list(s) in the captioned proceeding(s), 
and the respective electric utility regulatory agencies in New York, 
New Jersey and Pennsylvania.
    Comment date: May 28, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

8. Southern Energy Retail Trading; and Marketing, Inc.; CL Power 
Sales Nine, L.L.C.; Calpine Power Services Company; H.Q. Energy 
Services (U.S.) Inc.; CL Power Sales Twelve, L.L.C.; CL Power Sales 
Eleven, L.L.C.; ConAgra Energy Service, Inc.; West Georgia 
Generating Company, L.P.; NIPSCO Energy Service Inc.; PP&L 
EnergyPlus Co.; LG&E Energy Marketing Inc.; CNG Retail Services 
Corporation; CNG Power Services Corporation; North American Energy 
Conservation, Inc.

[Docket Nos. ER98-1149-003; ER96-2652-030; ER94-1545-017; ER97-851-008; 
ER99-893-001; ER99-894-001; ER95-1751-014; ER97-1686-006; ER96-1431-
011; ER98-4608-003; ER94-1188-027; ER97-1845-007; ER94-1554-020; ER94-
152-021]

    Take notice that on April 30, 1999, the above-mentioned power 
marketers filed quarterly reports with the Commission in the above-
mentioned proceedings for information only. These filings are available 
for public inspection and copying in the Public Reference Room or on 
the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

9. Shamrock Trading, LLC

[Docket No. ER98-3526-003]

    Take notice that on April 28, 1999, the above-mentioned power 
marketer filed a quarterly report with the Commission in the above-
mentioned proceeding for information only. This filing is available for 
public inspection and copying in the Public Reference Room or on the 
web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

10. ISO New England Inc.; Southern Energy Trading and Marketing, 
Inc. ; New Millennium Energy Corporation; WPS-Power Development, 
Inc.; Electric Clearinghouse, Inc.; PG&E Energy Trading--Power; 
CLECO Corporation; AEP Power Marketing, Inc.; Sempra Energy Trading 
Corp.; Unitil Resources, Inc.; West Penn Power Company dba 
Allegheny Energy; Energy International Power Marketing Corporation; 
Clinton Energy Management Services, Inc.

[Docket Nos. ER98-3554-003; ER95-976-016; ER97-2681-005; ER96-1088-023; 
ER94-968-026; ER95-1625-019; ER96-2677-005; ER96-2495-010; ER94-1691-
024; ER97-2460-005; ER96-2673-010; ER98-2059-004; ER98-3934-003]

    Take notice that on April 30, 1999, the above-mentioned power 
marketers filed quarterly reports with the Commission in the above-
mentioned proceedings for information only. These filings are available 
for public inspection and copying in the Public Reference Room or on 
the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

11. People's Electric Corporation and Penobscott Bay Energy Co.

[Docket No. ER98-3719-003 and Docket No. ER97-2875-005]

    Take notice that on April 29, 1999, the above-mentioned power 
marketers filed quarterly reports with the Commission in the above-
mentioned proceedings for information only. These filings are available 
for public inspection and copying in the Public Reference Room or on 
the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
(call 202-208-2222 for assistance).

12. Continental Energy Services, L.L.C.

[Docket No. ER98-4191-000]

    Take notice that on April 29, 1999, CMS Energy filed a letter with 
the Federal Energy Regulatory Commission stating that Continental 
Energy Services, L.L.C. (CES) was dissolved in the acquisition of 
Continental Natural Gas, Inc. by CMS Energy effective October 15, 1998. 
Therefore, CMS Energy no longer has CES and will not be participating 
in any electric ventures.
    Comment date: May 19, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

13. New England Power Pool

[Docket No. ER99-1374-001; ER99-1556-001; and ER99-1609-001]

    Take notice that on April 30, 1999, the New England Power Pool 
(NEPOOL) Executive Committee tendered four revised Market Rules and 
Procedures in compliance with the Commission's April 6, 1999, order in 
the captioned dockets (87 FERC para. 61,045), to be effective for all 
NEPOOL market transactions occurring after the Second Effective Date, 
which is now projected to occur on May 1, 1999.
    The NEPOOL Executive Committee states that copies of these 
materials were sent to all entities on the service lists in the 
captioned dockets, to all participants in the New England Power Pool, 
the New England state governors and regulatory commissions.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

14. Virginia Electric and Power Company

[Docket No. ER99-1885-000]

    Take notice that on April 30, 1999, Virginia Electric and Power 
Company (Virginia Power), tendered for filing two (2) executed Service 
Agreements for Long Term Firm Point-to-Point Transmission Service with 
The Wholesale Power Group under the Open Access Transmission Tariff to 
Eligible Purchasers dated July 14, 1997. Under the tendered Service 
Agreements, Virginia Power will provide Long Term Firm Point-to-Point 
Transmission Service to the Transmission Customer under the rates, 
terms and conditions of the Open Access Transmission Tariff.
    Virginia Power requests an effective date of January 1, 2000.
    Copies of the filing were served upon The Wholesale Power Group, 
the Virginia State Corporation Commission and the North Carolina 
Utilities Commission.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

15. Avista Corporation

[Docket No. ER99-2056-001]

    Take notice that on April 30, 1999, Avista Corporation (Avista 
Corp.), tendered for filing with the Federal Energy Regulatory 
Commission pursuant to 18 CFR 35.19(a) a refund report as ordered under 
the above referenced docket.
    A copy of this filing has been served upon East Greenacres 
Irrigation District and The United States Department of the Interior, 
Bureau of Reclamation.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

16. PacifiCorp

[Docket No. ER99-2691-000]

    Take notice that on April 30, 1999, PacifiCorp tendered for filing 
in

[[Page 26392]]

accordance with 18 CFR 35 of the Commission's Rules and Regulations, 
Revisions to the Network Transmission Service Agreement between 
PacifiCorp's Transmission Function and PacifiCorp's Merchant Function.
    Copies of this filing were supplied to the Washington Utilities and 
Transportation Commission and the Public Utility Commission of Oregon.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

17. New England Power Pool

[Docket No. ER99-2692-000]

    Take notice that on April 30, 1999, the New England Power Pool 
(NEPOOL), Executive Committee tendered for filing new Appendices to 
assist in the administration action of the NEPOOL Market Rules (the 
Market Rules). NEPOOL has requested that the Appendices to the Market 
Rules apply for administration of all NEPOOL market transactions 
occurring after the Second Effective Date, which is now projected to 
occur on May 1, 1999.
    The NEPOOL Executive Committee states that copies of these 
materials were sent to all participants in the New England Power Pool, 
the New England state governors and regulatory commissions.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

18. Northeast Utilities Service Company

[Docket No. ER99-2698-000]

    Take notice that on April 30, 1999, Northeast Utilities Service 
Company (NUSCO), on behalf of The Connecticut Light and Power Company, 
tendered for filing pursuant to Section 205 of the Federal Power Act 
and Section 35.13 of the Commission's Regulations, a rate schedule 
change for sales of electric energy to Connecticut Municipal Electric 
Energy Cooperative.
    NUSCO states that a copy of this filing has been mailed to 
Connecticut Municipal Electric Energy Cooperative and the Connecticut 
Department of Public Utility Control.
    NUSCO requests that the rate schedule change become effective on 
May 1, 1999.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

19. PECO Energy Company

[Docket No. ER99-2699-000]

    Take notice that on April 30, 1999, PECO Energy Company (PECO), 
tendered for filing under Section 205 of the Federal Power Act, 16 
U.S.C. S 792 et seq., a Transaction Letter dated April 30, 1999 with 
Horizon Energy Company d/b/a Exelon Energy (EXELON) under PECO's FERC 
Electric Tariff Original Volume No. 1 (Tariff).
    PECO requests an effective date of May 1, 1999, for the Transaction 
Letter.
    PECO states that copies of this filing have been supplied to EXELON 
and to the Pennsylvania Public Utility Commission.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

20. New England Power Pool

[Docket No. ER99-2700-000]

    Take notice that on April 30, 1999, the New England Power Pool 
Executive Committee tendered for filing a signature page to the New 
England Power Pool (NEPOOL), Agreement dated September 1, 1971, as 
amended, signed by DukeSolutions, Inc., (DukeSolutions). The NEPOOL 
Agreement has been designated NEPOOL FPC No. 2.
    The Executive Committee states that the Commission's acceptance of 
DukeSolutions's signature page would permit NEPOOL to expand its 
membership to include DukeSolutions. NEPOOL further states that the 
filed signature page does not change the NEPOOL Agreement in any 
manner, other than to make DukeSolutions a member in NEPOOL.
    NEPOOL requests an effective date of May 1, 1999, for commencement 
of participation in NEPOOL by DukeSolutions.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

21. MidAmerican Energy Company

[Docket No. ER99-2705-000]

    Take notice that on April 30, 1999, MidAmerican Energy 
Company(MidAmerican), tendered for filing a proposed change in its Rate 
Schedule for Power Sales, FERC Electric Rate Schedule, Original Volume 
No. 5. The proposed change consists of certain reused tariff sheets 
consistent with the quarterly filing requirement.
    MidAmerican states that it is submitting these tariff sheets for 
the purpose of complying with the requirements set forth in Southern 
Company Services, Inc., 75 FERC para. 61,130 (1996), relating to 
quarterly filings by public utilities of summaries of short-term 
market-based power transactions. The tariff sheets contain summaries of 
such transactions under the Rate Schedule for Power Sales for the 
applicable quarter.
    MidAmerican proposes an effective date of the first day of the 
applicable quarter for the rate schedule change. Accordingly, 
MidAmerican requests a waiver of the 60-day notice requirement for this 
filing. MidAmerican states that this date is consistent with the 
requirements of the Southern Company Services, Inc., order and the 
effective date authorized in Docket No. ER96-2459-000.
    Copies of the filing were served upon MidAmerican's customers under 
the Rate Schedule for Power Sales and the Iowa Utilities Board, the 
Illinois Commerce Commission and the South Dakota Public Utilities 
Commission.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

22. PacifiCorp

[Docket No. ER99-2715-000]

    Take notice that on April 30, 1999, PacifiCorp tendered for filing 
with the Federal Energy Regulatory Commission pursuant to 18 CFR, 
Section 35.13, a Certificate of Concurrence in Puget Sound Energy, 
Inc.'s filing regarding the 1998-99 Operating Procedures under the 
Pacific Northwest Coordination Agreement Docket No. ER99-2026-000, 
previously noticed on March 5, 1999.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

23. Milford Power Limited Partnership

[Docket No. ER99-2716-000]

    Take notice that on April 30, 1999, Milford Power Limited 
Partnership (Milford), tendered for filing a revised rate schedule and 
request for certain waivers and authorizations under various 
regulations of the Federal Energy Regulatory Commission (the 
Commission), in compliance with New England Power Pool, 85 FERC para. 
61,379 and consistent with Edison Mission Marketing & Trading., Inc., 
86 FERC para. 61,072.
    Milford has requested that the Commission establish an effective 
date of April 1, 1999, for the rate schedule.
    A copy of the filing was served upon the Massachusetts Department 
of Public Utilities.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

24. Consumers Energy Company

[Docket No. ER99-2717-000]

    Take notice that on April 30, 1999, Consumers Energy Company 
(Consumers), tendered for filing 5 executed service agreements for 
unbundled wholesale power service

[[Page 26393]]

pursuant to Consumers' Market Based Power Sales Tariff accepted for 
filing in Docket No. ER97-964-000. The service agreements all have 
effective dates of April 14, 1999 and are with the following customers:

1. Commonwealth Edison Co.
2. Duke Power
3. Duke Solutions, Inc.
4. Minnesota Power, Inc.
5. Cinergy Services, Inc.

    Copies of the filing have been served on the Michigan Public 
Service Commission and the customers listed above.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

25. Northeast Utilities Service Company

[Docket No. ER99-2719-000]

    Take notice that on April 30, 1999, Northeast Utilities Service 
Company (NUSCO) on behalf of its affiliate, Public Service Company of 
New Hampshire tendered for filing a Letter Agreement with Fitchburg Gas 
and Electric Light Company (FG&E).
    NUSCO requests an effective date the later of May 1, 1999, or the 
date the Second Effective Date market rules become effective in New 
England.
    NUSCO states that a copy of this filing was mailed to FG&E.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

26. Georgia Power Company

[Docket No. ER99-2720-000]

    Take notice that on April 30, 1999, Georgia Power Company tendered 
for filing a Service Agreement by and among itself and Oglethorpe Power 
Corporation pursuant to which Georgia Power Company will make wholesale 
power sales to Oglethorpe Power Corporation for a term in excess of one 
(1) year. The Service Agreement supersedes and replaces the Block Power 
Sale Agreement, Rate Schedule FERC No. 827, in its entirety.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

27. Duke Energy Moss Landing LLC

[Docket No. ER99-2721-000]

    Take notice that on April 30, 1999, pursuant to Section 205 of the 
Federal Power act and Section 35.15(a), 18 CFR 35.15(a) of the 
Commission's Regulations, Duke Energy Moss Landing LLC (Moss Landing), 
tendered for filing with the Federal Energy Regulatory Commission a 
Notice of Termination of the Must-Run Rate Schedule between Moss 
Landing and the California Independent System Operator Corporation as 
the Must-Run Rate Schedule applies to Unit 7, designated as Moss 
Landing's FERC Rate Schedule No. 2.
    Additionally, pursuant to Section 35.15(a) of the Commission's 
Regulations, Moss Landing requests an effective date for this 
termination of June 30, 1999.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

28. Commonwealth Electric Company

[Docket No. ER99-2723-000]

    Take notice that on April 30,1999, Commonwealth Electric Company 
(Commonwealth), tendered for filing the Service Agreement for Network 
Integration Transmission, Network Operating Agreement, Interconnection 
Agreement and Distribution Service Agreement between Commonwealth 
Electric Company and Massachusetts Bay Transportation Authority (MBTA).
    The MBTA seeks to take service on May 1, 1999 in order for the MBTA 
to obtain the electric energy it has already purchased from BECo. 
Therefore, Commonwealth respectfully requests an effective date of May 
1, 1999, for the above Agreements and respectfully requests waiver of 
the waiver of any portion of the Commission's Regulations that are not 
satisfied by the enclosed information.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

29. Milford Power Limited Partnership

[Docket No. ER99-2729-000]

    Take notice that on April 30, 1999, Milford Power Limited 
Partnership (Milford), tendered for filing an umbrella service 
agreement for short-term power sales from Milford's electric generation 
facility located in Milford, Massachusetts to Select Energy, Inc., and 
requests waiver of the Commission's prior notice requirement.
    Milford has requested that the Commission establish an effective 
date of April 1, 1999, for the service agreement.
    A copy of the filing was served upon the Massachusetts Department 
of Public Utilities.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

30. Entergy Services, Inc.

[Docket No. ER99-2731-000]

    Take notice that on April 30, 1999, Entergy Services, Inc. (Entergy 
Services), on behalf of Entergy Arkansas, Inc. (EAI), tendered for 
filing a Long-Term Market Rate Service Agreement between EAI and Union 
Electric Company d/b/a Ameren UE for the sale of power under Entergy 
Services' Rate Schedule SP.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

31. New England Power Pool

[Docket No. ER99-2732-000]

    Take notice that on April 30, 1999, the New England Power Pool 
Executive Committee tendered for filing a signature page to the New 
England Power Pool (NEPOOL) Agreement dated September 1, 1971, as 
amended, signed by DukeSolutions, Inc., (DukeSolutions). The NEPOOL 
Agreement has been designated NEPOOL FPC No. 2.
    The Executive Committee states that the Commission's acceptance of 
DukeSolutions's signature page would permit NEPOOL to expand its 
membership to include DukeSolutions. NEPOOL further states that the 
filed signature page does not change the NEPOOL Agreement in any 
manner, other than to make DukeSolutions a member in NEPOOL.
    NEPOOL requests an effective date of May 1, 1999, for commencement 
of participation in NEPOOL by DukeSolutions.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

32. Central Vermont Public Service Corporation

[Docket No. ER99-2733-000]

    Take notice that on April 30, 1999, Central Vermont Public Service 
Corporation (Central Vermont), tendered for filing an amended and 
restated market-based sales tariff (MR Tariff). The MR Tariff revises 
the terms and conditions upon which Central Vermont makes sales of 
capacity and/or energy available at market-based rates and resells 
transmission rights on a short-term or long-term basis. The MR Tariff 
also allows Central Vermont to sell ancillary services at market-based 
rates in NEPOOL's ancillary services markets.
    The MR Tariff will supersede Central Vermont's existing market-
based sales tariff accepted in Docket No. ER98-2329-001 and all new 
transactions will be subject to the new MR Tariff. Central Vermont 
requests waiver of the Commission's notice requirements so that the MR 
Tariff may become effective on May 1, 1999, the day NEPOOL's ancillary 
service markets are expected to begin operation.

[[Page 26394]]

    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

33. Commonwealth Edison Company

[Docket No. ER99-2734-000]

    Take notice that on April 30, 1999, Commonwealth Edison Company 
(ComEd), tendered for filing a revised Index of Customers to correct 
references to the and date of Service Agreements between ComEd and 
Avista Energy, Inc. (Avista), Niagara Mohawk Energy Marketing, Inc., 
(NIMO) and Tenaska Power Services Company (Tenaska) under the terms of 
ComEd's Open Access Transmission Tariff (OATT). ComEd also submitted an 
unexecuted Service Agreement establishing Tenaska as a short-term firm 
customer under the terms of ComEd's Open Access Transmission Tariff 
(OATT).
    ComEd requests an effective date of April 1, 1998, for the short-
term firm service agreement with Tenaska to coincide with the first day 
of service to Tenaska under this type of Service Agreement.
    Copies of this filing were served on Avista, NIMO, and Tenaska.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

34. Illinois Power Company

[Docket No. ER99-2735-000]

    Take notice that on April 30, 1999, Illinois Power Company 
(Illinois Power), 500 South 27th Street, Decatur, Illinois 62526, 
tendered for filing updated specification pages to the existing Network 
Service Agreement under which Soyland Power Cooperative will take 
transmission service pursuant to its open access transmission tariff. 
The agreements are based on the Form of Service Agreement in Illinois 
Power's tariff.
    Illinois Power has requested an effective date of April 1, 1999.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

35. American Electric Power Service Corporation

[Docket No. ER99-2753-000]

    Take notice that on April 30, 1999, the American Electric Power 
Service Corporation (AEPSC), tendered for filing service agreements by 
the AEP Companies under the Wholesale Market Tariff of the AEP 
Operating Companies (Power Sales Tariff). The Power Sales Tariff was 
accepted for filing effective October 10, 1997 and has been designated 
AEP Operating Companies' FERC Electric Tariff Original Volume No. 5.
    AEPSC respectfully requests waiver of notice to permit these 
service agreements to be made effective for service as specified in the 
submittal letter to the Commission with this filing.
    A copy of the filing was served upon the Parties and the State 
Utility Regulatory Commissions of Indiana, Kentucky, Michigan, Ohio, 
Tennessee, Virginia and West Virginia.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

36. Northeast Utilities Service Company

[Docket No. ER99-2761-000]

    Take notice that on April 30, 1999, Northeast Utilities Service 
Company (NUSCO), on behalf of The Connecticut Light and Power Company, 
tendered for filing pursuant to Section 205 of the Federal Power Act 
and Section 35.13 of the Commission's Regulations, a rate schedule 
change for sales of electric energy to Town of Wallingford, 
Connecticut, Department of Public Utilities and Connecticut Municipal 
Electric Energy Cooperative.
    NUSCO states that a copy of this filing has been mailed to Town of 
Wallingford, Connecticut, Department of Public Utilities, Connecticut 
Municipal Electric Energy Cooperative and the Connecticut Department of 
Public Utility Control.
    NUSCO requests that the rate schedule change become effective on 
May 1, 1999.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

37. San Diego Gas & Electric Company

[Docket No. ER99-2762-000]

    Take notice that on April 30, 1999, San Diego Gas and Electric 
Company (SDG&E), tendered for filing certain tariff sheets in its 
Transmission Owner Tariff (TO Tariff) to supersede TO Tariff No. 47 and 
add new Original TO Tariff Sheet Nos. 67 through 77.
    SDG&E requests an effective date of July 1, 1999
    SDG&E states the instant filing is submitted to provide for the 
recovery from End Use Customers of Reliability Must Run charges billed 
by the California Independent Operator Corporation to SDG&E in its 
capacity as a Participating Transmission Owner for services provided 
under the RMR Contracts for Encina, South Bay and the combustion 
turbines located in SDG&E's service area.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

38. Western Systems Power Pool

[Docket No. ER99-2763-000]

    Take notice that on April 30, 1999, the Western Systems Power Pool 
(WSPP), tendered for filing certain revisions to the WSPP Agreement. 
The WSPP states the revisions to the WSPP Agreement are necessary to 
update the terms of the WSPP Agreement and better ensure commercial 
enforceability of the agreements terms.
    WSPP seeks an effective date of June 1, 1999, for this filing.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

39. Delmarva Power & Light Company and Atlantic City Electric 
Company

[Docket No. ER99-2781-000]

    Take notice that on April 30, 1999, Delmarva Power & Light Company 
(Delmarva) and Atlantic City Electric Company (Atlantic) tendered for 
filing amendments to Delmarva's and Atlantic's market-based rate tariff 
filings in response to the Federal Energy Regulatory Commission's 
(FERC) March 16, 1999, deficiency letter in the above-captioned 
proceedings. This filing includes (1) Revisions to Delmarva's and 
Atlantic's market-based rate tariffs; (2) notice of the withdrawal of 
the service agreements pursuant to which Delmarva and Atlantic would 
have been eligible for service under each other's market-based rate 
tariffs in Docket Nos. ER99-1839-000 and ER99-1898-000; and (3) a 
separate power sales agreement between Delmarva and Atlantic to allow 
capacity credit transactions at the market prices established by the 
PJM Power Exchange.
    Delmarva and Atlantic request an effective date of January 15, 1999 
for the revisions to their market-rate sales tariffs and January 18, 
1999 for the Capacity Credit Agreement.
    Delmarva and Atlantic state that copies of this filing have been 
served upon all the customers under their market-based rate tariffs.
    Comment date: May 20, 1999, in accordance with Standard Paragraph E 
at the end of this notice.

Standard Paragraphs:

    Any person desiring to be heard or to protest such filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 888 First Street, NE, Washington, DC 20426, in 
accordance with Rules 211 and 214 of the Commission's Rules of Practice 
and Procedure (18 CFR 385.211 and 385.214). All such motions or 
protests should be filed on or before the comment date. Protests will 
be

[[Page 26395]]

considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a motion to 
intervene. Copies of these filings are on file with the Commission and 
are available for public inspection. This filing may also be viewed on 
the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-208-
2222 for assistance).
David P. Boergers,
Secretary.
[FR Doc. 99-12239 Filed 5-13-99; 8:45 am]
BILLING CODE 6717-01-P