[Federal Register Volume 75, Number 229 (Tuesday, November 30, 2010)]
[Notices]
[Pages 74042-74043]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2010-30067]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Western Area Power Administration

[DOE/EIS-0462]


Intent To Prepare an Environmental Impact Statement and To 
Conduct Scoping Meetings: Interconnection of the Proposed Crowned Ridge 
Wind Energy Center Project, South Dakota

AGENCY: Western Area Power Administration, DOE.

ACTION: Notice of Intent To Prepare an Environmental Impact Statement 
and To Conduct Scoping Meetings; Notice of Floodplain and Wetlands 
Involvement.

-----------------------------------------------------------------------

SUMMARY: NextEra Energy Resources (NextEra) applied to interconnect its 
proposed 150-megawatt (MW) Crowned Ridge Wind Energy Center Project 
(Project) with the Western Area Power Administration's (Western) 
existing Watertown Substation in Codington County, South Dakota. The 
proposed Project would be located in Codington and Grant counties, 
South Dakota. Western will prepare an environmental impact statement 
(EIS) on the proposal to interconnect the Project in accordance with 
the National Environmental Policy Act of 1969 (NEPA), U.S. Department 
of Energy (DOE) NEPA Implementing Procedures, and the Council on 
Environmental Quality (CEQ) regulations for implementing NEPA.
    Western's need for agency action is precipitated by NextEra's 
application to interconnect with Western's power transmission system. 
Western needs to consider NextEra's interconnection request under its 
Open Access Transmission Service Tariff (Tariff). This EIS will address 
Western's Federal action of interconnecting the proposed Project to 
Western's transmission system, making changes within Western's existing 
Watertown Substation to physically connect NextEra's proposed Project, 
and making any necessary system modifications to accommodate the 
interconnection. By taking these actions, power generated by NextEra's 
proposed Project would use Western's transmission system to reach the 
market.
    Portions of NextEra's proposed Project may affect floodplains and 
wetlands, so this Notice of Intent (NOI) also serves as a notice of 
proposed floodplain or wetland action in accordance with DOE floodplain 
and wetland environmental review requirements.

DATES: A public scoping meeting will be held on December 15, 2011, from 
5 p.m. to 8 p.m. in Watertown, South Dakota.
    The public scoping period starts with the publication of this 
notice and ends on January 14, 2011. Western will consider all comments 
on the scope of the EIS received or postmarked by that date. The public 
is invited to submit comments on the proposed Project at any time 
during the EIS process.

ADDRESSES: Western will host public scoping meetings at the Watertown 
Public Library Community Room, 160 6th Street North, Watertown, South 
Dakota, to provide information on the Project and gather comments on 
the proposal. Oral or written comments may be provided at the public 
scoping meetings or mailed or e-mailed to Matt Marsh, Upper Great 
Plains Regional Office, Western Area Power Administration, P.O. Box 
35800, Billings, MT 59107-5800, e-mail [email protected], telephone (800) 
358-3415.

FOR FURTHER INFORMATION CONTACT: For additional information on the 
proposed Project, the EIS process, or to receive a copy of the Draft 
EIS when it is published, contact Matt Marsh at the addresses above. 
For general information on the DOE's NEPA review process, contact Carol 
M. Borgstrom, Director, Office of NEPA Policy and Compliance, GC-54, 
U.S. Department of Energy, 1000 Independence Avenue, SW., Washington, 
DC 20585-0119, telephone (202) 586-4600 or (800) 472-2756, facsimile 
(202) 586-7031.

SUPPLEMENTARY INFORMATION: Western is a Federal power marketing agency 
within the DOE that markets and delivers Federal wholesale electric 
power (principally hydroelectric power) to municipalities, rural 
electric cooperatives, public utilities, irrigation districts, Federal 
and State agencies, and Native American tribes in 15 western and 
central States. NextEra's proposed Project would be located within 
Western's Upper Great Plains Region, which operates in North and South 
Dakota, most of Montana, and portions of Iowa, Minnesota, and Nebraska. 
NextEra applied to interconnect their proposed 150-MW Project with 
Western's existing Watertown Substation in Codington County, South 
Dakota. The proposed wind farm Project would be located entirely on 
private lands; no State- or Federal-managed land would be affected. 
There are no designated cooperating agencies at this time, but 
cooperating agencies could be identified at a later date.
    Western will prepare an EIS on the interconnection of the proposed 
Project in accordance with NEPA (42 U.S.C. 4321-4347); DOE NEPA 
Implementing Procedures (10 CFR part 1021), and the CEQ regulations for 
implementing NEPA (40 CFR parts 1500-1508).\1\
---------------------------------------------------------------------------

    \1\ On October 4, 1999, DOE's Assistant Secretary for 
Environmental, Safety and Health delegated to Western's 
Administrator the authority to approve EISs for integrating 
transmission facilities with Western's transmission grid.
---------------------------------------------------------------------------

Purpose and Need for Agency Action

    Western's need for agency action is precipitated by NextEra's 
application to interconnect with Western's power transmission system. 
Western needs to consider NextEra's interconnection request under 
Western's Tariff, which provides for open access to its transmission 
system through an interconnection if there is available capacity in the 
transmission system. This EIS will address Western's Federal action of 
interconnecting NextEra's proposed Project with Watertown Substation, 
making changes within the substation to physically accomplish the 
interconnection, and making any necessary system modifications to 
accommodate the interconnection. Preliminary studies indicate that the 
power system can accommodate the proposed interconnection without 
negatively affecting system reliability or power deliveries to existing 
customers. The transmission system may require network and/or 
transmission system upgrades as determined in the final studies. Any 
such upgrades would be funded by NextEra as a condition of the 
interconnection.

Proposed Action

    In compliance with the provisions of the Tariff, and considering 
the environmental impacts of NextEra's proposed Project as identified 
by the EIS process, Western will consider NextEra's interconnection 
request. If approved the necessary changes within Watertown Substation 
would be made to accomplish the interconnection, and power generated by 
the proposed Project would use Western's transmission system to reach 
the

[[Page 74043]]

market. Western will consult with the U.S. Fish and Wildlife Service 
under section 7 of the Endangered Species Act and with the South Dakota 
State Historic Preservation Office under section 106 of the National 
Historic Preservation Act.

Alternatives

    Western must respond to NextEra's proposed Project as it is 
described in the interconnection application, and make a decision on 
interconnection based on that application. However, Western will use 
the information in NextEra's interconnection request to evaluate 
possible options for transmission line approaches to Watertown 
Substation. The location of the interconnection bay within the 
substation, other transmission lines, and any future development plans 
will all be considered in siting the approach. Under the no action 
alternative, Western would not approve the interconnection request, nor 
construct the interconnection facility.

Applicant's Proposed Project

    NextEra's proposed Project would consist of up to 100 wind turbine 
generators with a combined total generating capacity of 150 MW, located 
within an approximately 20,000-acre site in Codington and Grant 
counties, northeast of Watertown and east of Interstate 29. The 
turbines would be located in short east-west or southwest-northeast 
oriented strings, with the strings widely scattered over an area of 
roughly 6 by 11 miles in size. Each turbine would be approximately 389 
feet tall from tip of blade to base, and 262 feet tall from the ground 
to the hub. In addition to the turbines, other proposed Project 
facilities would include all-weather access roads to each turbine 
location; underground power collection lines linking turbines to the 
Project collector substation; the Project collector substation; an 
approximately 15-mile-long high-voltage transmission line linking the 
collector substation to Western's Watertown Substation; operation and 
maintenance facilities and yard; Supervisory Control and Data 
Acquisition equipment and metering equipment; and two or three 
permanent meteorological towers.
    While Western's Federal action is to consider the interconnection 
request and the physical interconnection to Western's existing 
substation, the EIS will also identify and review the environmental 
impacts of NextEra's proposed Project. NextEra will be responsible for 
completing necessary coordination with State and local agencies to 
permit their proposed Project.
    NextEra intends to provide renewable energy to local utilities in 
response to South Dakota's Renewable Energy Portfolio Standards, passed 
in 2008, which mandate that 10 percent of all electricity consumed in 
the State be produced from renewable sources by 2015.

Floodplain or Wetland Involvement

    Floodplains and wetlands are common in this part of South Dakota. 
Since the proposed Project may involve action in floodplains or 
wetlands, this NOI also serves as a notice of proposed floodplain or 
wetland action. The EIS will include a floodplain/wetland assessment 
and floodplain/wetland statement of findings following DOE regulations 
for compliance with floodplain and wetlands environmental review (10 
CFR part 1022).

Environmental Issues

    The location of the proposed Project is in a relatively sparsely 
populated portion of eastern South Dakota. The area is characterized by 
extensive agriculture and pasture with scattered farmsteads on section 
line roads. NextEra has secured leases with willing landowners for its 
wind generation turbines and related facilities. Available overview 
information indicates this area has a relatively low probability of 
substantial natural resources conflicts. NextEra's siting process for 
the wind turbine strings and associated facilities considered sensitive 
resources, and the proposed Project was designed to avoid these areas. 
The EIS will evaluate the level of impact the interconnection and 
NextEra's proposed Project would have on environmental resources within 
the 20,000-acre site, which may lead to minor modifications in the 
proposed Project to further avoid or minimize resource impacts. While 
no substantive resource conflicts have been identified thus far, the 
EIS will analyze the potential impacts on potentially affected 
environmental resources. Wind farm projects are generally known to have 
visual and noise effects, and may affect birds and bats.

Public Participation

    Interested parties are invited to participate in the scoping 
process to help define the scope, significant resources, and issues to 
be analyzed in depth, and to eliminate from detailed study issues that 
are not pertinent. The scoping process will involve all interested 
agencies (Federal, State, county, and local), Native American tribes, 
public interest groups, businesses, affected landowners, and individual 
members of the public.
    Western will consult with potentially affected or interested tribes 
to jointly evaluate and address the potential effects on cultural 
resources, traditional cultural properties, or other resources 
important to the tribes. These nation-to-nation consultations will be 
conducted in accordance with Executive Order 13175, Consultation and 
Coordination with Indian Tribal Governments (65 FR 67249), the 
President's memorandum of April 29, 1994, Government-to-Government 
Relations with Native American Tribal Governments (59 FR 22951), DOE-
specific guidance on tribal interactions, and applicable natural and 
cultural resources laws and regulations.
    A public scoping meeting will be held as described under DATES and 
ADDRESSES above. The meeting will be informal, and attendees will be 
able to speak directly with Western and NextEra representatives about 
the proposed Project. The public is encouraged to provide information 
and comments on issues it believes Western should address in the EIS. 
Comments may be broad in nature or restricted to specific areas of 
concern. After gathering comments on the scope of the EIS, Western will 
address those issues raised in the EIS. Comments on Western's proposed 
action and NextEra's proposed Project will be accepted at any time 
during the EIS process, and may be directed to Western as described 
under ADDRESSES above.
    Western's EIS process will include the public scoping meetings; 
consultation and coordination with appropriate Federal, State, county, 
and local agencies and tribal governments; involvement with affected 
landowners; distribution of and public review and comment on the Draft 
EIS; a formal public hearing or hearings on the Draft EIS; distribution 
of a published Final EIS; and publication of Western's Record of 
Decision in the Federal Register.

    Dated: November 19, 2010.
Timothy J. Meeks,
Administrator.
[FR Doc. 2010-30067 Filed 11-29-10; 8:45 am]
BILLING CODE 6450-01-P