Military Construction: Kaiserslautern Military Community Center  
Project Continues to Experience Problems (25-JUN-08,		 
GAO-08-923T).							 
                                                                 
The Kaiserslautern Military Community Center (KMCC) is one of	 
many projects initiated at Ramstein Air Base to upgrade 	 
capabilities of the base as a result of the consolidation of	 
military bases in Europe. The KMCC is intended to provide	 
lodging, dining, shopping, and entertainment for thousands of	 
U.S. military and civilian personnel and their families in the	 
area. Construction on the project, which began in late 2003, was 
originally scheduled to be completed in early 2006. On June 28,  
2007, GAO testified that construction deficiencies and		 
mismanagement had drawn into question when the project would be  
completed and at what cost. This testimony discusses updated	 
findings related to the KMCC project. The testimony describes (1)
the current status of the KMCC construction project, (2) whether 
oversight and internal control improvements have been made by the
Air Force since GAO's last testimony, and (3) if other projects  
recently completed in the KMCC area have experienced problems	 
similar to those affecting the KMCC. To address the objectives,  
GAO interviewed officials from the U.S. Air Force, Army and Air  
Force Exchange Service (AAFES), Air Force Services Agency, U.S.  
Army Corps of Engineers, Department of State, and German	 
government. GAO also conducted site visits and reviewed project  
plans, cost estimates, completion analyses, and other relevant	 
KMCC documents. 						 
-------------------------Indexing Terms------------------------- 
REPORTNUM:   GAO-08-923T					        
    ACCNO:   A82530						        
  TITLE:     Military Construction: Kaiserslautern Military Community 
Center Project Continues to Experience Problems 		 
     DATE:   06/25/2008 
  SUBJECT:   Air Force bases					 
	     Air Force facilities				 
	     Air Force personnel				 
	     Air Force procurement				 
	     Construction contracts				 
	     Construction costs 				 
	     Contract modifications				 
	     Cost analysis					 
	     Erroneous payments 				 
	     Expense claims					 
	     Facility construction				 
	     Facility management				 
	     Federal property management			 
	     Financial management				 
	     Foreign governments				 
	     Funds management					 
	     Internal controls					 
	     Military cost control				 
	     Military facilities				 
	     Military facility construction			 
	     Military forces					 
	     Policy evaluation					 
	     Schedule slippages 				 
	     Cost estimates					 
	     Policies and procedures				 
	     Kaiserslautern Military Community Center		 
	     (KMCC)						 
                                                                 
	     Ramstein Air Base					 

******************************************************************
** This file contains an ASCII representation of the text of a  **
** GAO Product.                                                 **
**                                                              **
** No attempt has been made to display graphic images, although **
** figure captions are reproduced.  Tables are included, but    **
** may not resemble those in the printed version.               **
**                                                              **
** Please see the PDF (Portable Document Format) file, when     **
** available, for a complete electronic file of the printed     **
** document's contents.                                         **
**                                                              **
******************************************************************
GAO-08-923T

   

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to [email protected]. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Committee on Oversight and Government Reform, House of 
Representatives: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 10:00 a.m. EDT:
Wednesday, June 25, 2008: 

Military Construction: 

Kaiserslautern Military Community Center Project Continues to 
Experience Problems: 

Statement of Gregory D. Kutz, Managing Director: 
Forensic Audits and Special Investigations: 

Bruce A. Causseaux, Senior Level Specialist: 
Forensic Audits and Special Investigations: 

Terrell G. Dorn, Director:
Physical Infrastructure: 

GAO-08-923T: 

GAO Highlights: 

Highlights of GAO-08-923T, a testimony before the Committee on 
Oversight and Government Reform, House of Representatives. 

Why GAO Did This Study: 

The Kaiserslautern Military Community Center (KMCC) is one of many 
projects initiated at Ramstein Air Base to upgrade capabilities of the 
base as a result of the consolidation of military bases in Europe. The 
KMCC is intended to provide lodging, dining, shopping, and 
entertainment for thousands of U.S. military and civilian personnel and 
their families in the area. Construction on the project, which began in 
late 2003, was originally scheduled to be completed in early 2006. On 
June 28, 2007, GAO testified that construction deficiencies and 
mismanagement had drawn into question when the project would be 
completed and at what cost. 

This testimony discusses updated findings related to the KMCC project. 
The testimony describes (1) the current status of the KMCC construction 
project, (2) whether oversight and internal control improvements have 
been made by the Air Force since GAO�s last testimony, and (3) if other 
projects recently completed in the KMCC area have experienced problems 
similar to those affecting the KMCC. 

To address the objectives, GAO interviewed officials from the U.S. Air 
Force, Army and Air Force Exchange Service (AAFES), Air Force Services 
Agency, U.S. Army Corps of Engineers, Department of State, and German 
government. GAO also conducted site visits and reviewed project plans, 
cost estimates, completion analyses, and other relevant KMCC documents. 

What GAO Found: 

Approximately 1 year after GAO�s June 2007 testimony and over 2 years 
after the KMCC�s originally scheduled construction completion date, the 
project continues to experience significant cost and schedule 
uncertainty along with construction quality problems and ongoing 
criminal investigations. Limited progress has been made on KMCC 
construction, and there are still no accurate estimates of how much the 
total project will cost or when it will be completed. Major 
construction deficiencies GAO reported in 2007 are just now beginning 
to be corrected. The photos below show that other than floor tiles 
being installed, the food court area remains essentially the same as in 
2007 and still requires finishing work and the installation of 
restaurants. 

Figure: Photographs of the food court area, May 2007 and May 2008: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

In addition, the Air Force does not track the total cost of the KMCC. 
Specifically, tens of millions of dollars related to design, foreign 
currency fluctuation, rework, personnel, and furniture and equipment 
costs are not included in the Air Force�s cost estimates. Contingencies 
to fund items such as repairs to cracking concrete are also not 
included in the Air Force�s estimates. After including all estimated 
costs, the total cost of the project will likely exceed $200 million. 
Project delays have also resulted in additional costs to the U.S. 
government and lost profit for project funding partners. For example, 
AAFES estimates that it is losing $500,000 of profit for each month 
that the exchange facility is not open. 

Although these problems exist, the Air Force has made significant 
improvements in its oversight and control over the project. For 
example, the Air Force established standardized policies and procedures 
for reviewing change orders and invoices. Improvements in controls over 
payments and change orders have minimized future risks of paying for 
unapproved work or fraudulent billings for work not performed. 

Cost, schedule, and construction deficiencies affected other projects 
built by German government construction agents in the KMCC area. For 
example, underground electrical ducts at Ramstein Air Base flood with 
water causing runway lights to malfunction. A freight terminal on the 
air base was also built with structural deficiencies that resulted in 
its temporary evacuation. 

To view the full product, including the scope and methodology, click on 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-923T]. For more 
information, contact Gregory Kutz at (202) 512-6722 or [email protected] or 
Terrell Dorn at (202) 512-6923 or [email protected]. 

[End of section] 

Mr. Chairman and Members of the Committee: 

Thank you for the opportunity to discuss our findings on the current 
status of the Kaiserslautern Military Community Center (KMCC) 
construction project. This testimony is a 1-year update to our 
testimony before this committee in June 2007,[Footnote 1] which 
detailed the problems facing the project. In June 2007, we testified 
that the KMCC was experiencing cost, schedule, and construction quality 
problems that raised questions about when the project would be 
completed and at what cost. At the time of our testimony, there were 
few workers on-site, the building's roof was leaking, and German police 
and Air Force Office of Special Investigations (AFOSI) agents were 
seizing documents as part of ongoing criminal investigations. In 
addition, the projected total cost of the project had increased 
substantially because of delays, rework, and the appreciation of the 
euro versus the U.S. dollar. Our 2007 testimony also detailed 
construction management failures by the Landesbetrieb Liegenschafts- 
und Baubetreuung's office in Kaiserslautern (LBB-Kaiserslautern), the 
German construction agent charged with managing the project for the 
U.S. forces. In addition, our testimony detailed control weaknesses 
within the Air Force that contributed to the problems for the project. 
This testimony provides an update on the status of the KMCC project and 
its problems, and makes an assessment of whether other construction 
projects in the area have experienced similar problems. 

As we previously reported, the KMCC, an 844,000 square foot facility, 
is one of many projects that were initiated at Ramstein Air Base to 
upgrade capabilities of the base as a result of the consolidation of 
military bases in Europe. It is intended to provide lodging, dining, 
shopping, and entertainment for over 50,000 U.S. military and civilian 
personnel and their families in the Kaiserslautern, Germany, area. 
Project highlights include a 350-room visiting quarters, sports bar, 
name-brand restaurant, food court, and numerous retail businesses. 
Funding for the KMCC was provided from a variety of sources including 
nonappropriated funds from the Army and Air Force Exchange Service 
(AAFES) and the Air Force Services Agency (AFSVA), [Footnote 2] 
military construction appropriations, and the Rhein Main Transition 
Program (RMTP) funds.[Footnote 3] Construction on the KMCC began in 
November 2003 and was planned to be completed in early 2006. 

In addition, we previously reported that the activities of U.S. forces 
personnel in Germany are to be carried out in accordance with the 
provisions of the North Atlantic Treaty Organization's Status of Forces 
Agreement and various implementing agreements. The KMCC, like other 
military construction projects in Germany, is governed by one such 
agreement, the Auftragsbaugrundsaetze 1975 (ABG-75) Administrative 
Agreement. ABG-75 provides that U.S. forces are to coordinate 
construction planning with the German government to ensure the optimum 
use of German design and construction capacities. For the KMCC, the 
responsibility for construction resided with LBB-Kaiserslautern, a 
German government construction agency. 

As requested, this testimony updates our findings on the status of the 
project and problems affecting the KMCC. Specifically, the testimony 
will describe (1) the current status of the KMCC construction project, 
including projected costs, projected construction completion dates, and 
status of ongoing investigations; (2) whether oversight and internal 
control improvements have been made by the Air Force since our last 
testimony; and (3) whether other projects recently completed in the 
KMCC area have experienced problems similar to those affecting the 
KMCC. 

To address our objectives, we conducted interviews with Air Force 
personnel responsible for the KMCC project. In addition, we interviewed 
officials from LBB-Kaiserslautern, AAFES, AFSVA, and the U.S. Army 
Corps of Engineers. We also interviewed officials from the Department 
of State and officials from the Federal Republic of Germany's 
construction division. We obtained and reviewed project plans, cost 
completion analyses, and other relevant documents related to the design 
and construction of the KMCC. We also compiled Air Force and LBB- 
Kaiserslautern cost estimates for the various cost elements associated 
with the KMCC. We physically inspected the KMCC and other recently 
completed facilities on Ramstein Air Base. See appendix I for more 
details on our scope and methodology. 

Because of ongoing investigations, we were not able to fully explore 
and discuss the details of fraud investigations with AFOSI and the 
German police, which limited the scope of our audit work. 

We conducted this performance audit from November 2007 through June 
2008 in accordance with generally accepted government auditing 
standards. Those standards require that we plan and perform the audit 
to obtain sufficient, appropriate evidence to provide a reasonable 
basis for our findings and conclusions based on our audit objectives. 
We believe that the evidence obtained provides a reasonable basis for 
our findings and conclusions based on our audit objectives. 

Summary: 

Approximately 1 year after our initial testimony and over 2 years after 
the KMCC's originally scheduled construction completion date, the 
project continues to experience significant cost and schedule 
uncertainty along with construction quality problems and ongoing 
criminal investigations. Since our testimony in June 2007, limited 
progress has been made on KMCC construction, and there are still no 
accurate estimates of how much the total project will cost or when it 
will be completed. Delays in reaching completion agreements with major 
contractors have contributed to the lack of progress over the last 
year. In addition, major construction deficiencies, such as the leaking 
roof and improperly installed kitchen exhaust ducts, which we discussed 
during our initial testimony, are just now beginning to be corrected. 
For example, in February 2008, a $2.7 million[Footnote 4] contract was 
awarded for the first of four phases of repair work on the leaking 
roof, and in May 2008, a $1.2 million contract was awarded for the 
second phase of roof repairs. However, long cracks in concrete floors 
have been identified since our June 2007 testimony, which raise new 
concerns about construction quality and could result in additional time 
and cost to repair. While the number of workers on-site has increased 
in recent months, it is unclear whether the number and type of workers 
are sufficient to complete construction by LBB-Kaiserslautern's current 
projected date of January 2009. This projected date only represents 
construction completion; however, the facility will not be open to the 
public for about 4 months following construction completion. Finally, 
criminal and civil investigations continue to surround the project and 
indictments are expected, according to AFOSI agents. 

There are no accurate estimates of how much the total KMCC project will 
cost because the Air Force does not track all project costs. While the 
Air Force actively tracks what it considers to be core construction- 
related costs, tens of millions of dollars of other project costs are 
not included in Air Force cost estimates. Specifically, costs that are 
not included in the estimates are design costs, foreign currency 
fluctuation costs, costs for roof repair and other rework, personnel 
costs, and costs for furniture and equipment. Foreign currency 
fluctuation costs are of particular concern because of the significant 
appreciation of the euro versus the U.S. dollar since inception of the 
project. In total, the euro has appreciated 35 percent against the U.S. 
dollar since construction began on the KMCC in November 2003. In 
addition, contingencies to fund items such as potential hindrance 
claims[Footnote 5] and repairs to floor cracks are not included in the 
estimated construction costs for completion. When taking into account 
all estimated costs, the total cost of the project will likely exceed 
$200 million. This figure was derived by consolidating numerous Air 
Force cost estimates captured in different accounts, such as military 
construction funds, non-appropriated funds, and operations and 
maintenance funds. Project delays have also resulted in additional 
costs to the U.S. government and lost profit for AAFES and AFSVA. For 
example, AAFES, responsible for management of the new exchange, 
estimates that it is losing $500,000 of profit for each month that the 
exchange facility is not open. In addition, the Air Force also 
estimates that the U.S. government is paying an additional $90,000 each 
month when personnel traveling at the government's expense must stay 
off base because the hotel portion of the KMCC remains unfinished. 

Although problems exist with the project, the Air Force has made 
significant improvements in its oversight and internal controls. In 
June 2007, we reported that Air Force officials did not have adequate 
or appropriately qualified personnel assigned to the project and did 
not have effective oversight policies and controls in place. In the 
last year, the Air Force created the Resident Director's Office (RDO), 
which centralized management of the KMCC project and established 
standardized policies and procedures for reviewing invoices and change 
orders. According to the Air Force, the RDO has 29 personnel, which is 
a significant increase over the 8 oversight personnel initially 
assigned to the KMCC project. To minimize future risks of paying for 
unapproved work or fraudulent billings, the Air Force has also 
standardized its invoice and change order review processes. Finally, at 
various times in 2007 and 2008, senior Air Force officials engaged 
officials from the Department of State and the Federal Republic of 
Germany in an effort to identify options for generating progress on the 
project. 

Other projects recently completed in the KMCC area have also 
experienced problems similar to those affecting the KMCC. According to 
the Air Force, several recent projects built by LBB-Kaiserslautern 
associated with the RMTP on Ramstein Air Base have experienced 
significant cost and schedule growth as well as construction 
deficiencies. For example, the lights on the new south runway built on 
Ramstein Air Base are affected by a construction defect that allows 
groundwater to collect in the underground ducts and manholes that 
contain electrical components used to control the lights. The Air Force 
has repeatedly lost the capability to operate certain lights as a 
result of power outages caused by water intrusion to the lighting 
system and, when power outages occur, has been forced to divert 
aircraft to other air bases during periods of low visibility. The south 
runway also suffers from poor water drainage, in general, which at 
times causes large ponds to form between the south runway and adjacent 
taxiways. These ponds attract large waterfowl, which pose a safety risk 
to aircraft using the runway. Another reported example of construction 
deficiencies is illustrated by the newly constructed freight terminal, 
which must rely on additional support columns as a precaution to 
prevent the building's roofs from collapsing. Because of structural 
integrity issues, 41 additional columns were installed in the freight 
terminal to provide additional support to the roof. 

Progress on the KMCC Has Been Slow, Quality Problems Persist, and 
Project Costs Are Unknown: 

Approximately 1 year after our initial testimony and over 2 years after 
the KMCC's originally scheduled construction completion date, the 
project continues to experience significant cost and schedule 
uncertainty along with construction quality problems and ongoing 
criminal investigations. Since our testimony in June of 2007, limited 
progress has been made on KMCC construction, and estimates of how much 
the total project will cost or when it will be completed are uncertain. 
Total project costs are uncertain because the Air Force does not track 
all costs associated with the project. Specifically, tens of millions 
of dollars related to design, foreign currency fluctuation, rework, 
personnel, and furniture and equipment costs are not included in the 
Air Force's cost to date or estimate for construction completion of the 
project. Contingencies to fund items such as potential hindrance claims 
are also not included in the estimated costs for construction 
completion.[Footnote 6] When including all estimated costs, the total 
cost of the project will likely exceed $200 million. 

Limited Progress Has Been Made: 

Over the past year, limited progress has been made on constructing the 
KMCC, and the project's construction completion date is uncertain. 
Figures 1 and 2 show comparisons of the project when we visited in 2007 
and during our last visit in May 2008. The comparison of the KMCC food 
court area shows that other than some wall finishes and floor tiles 
being installed, the area remains essentially the same and still 
requires finishing work and the installation of the food court 
restaurants. Overall, relatively few contractor employees were on-site 
from the time of our initial site visit in May 2007 through early 2008, 
as LBB-Kaiserslautern experienced repeated delays in reaching 
agreements with major contractors to return to work. While LBB- 
Kaiserslautern reached completion agreements with its major contractors 
in March 2008, and the number of workers on-site has increased since 
that time, it is not clear if the number and type of workers are 
sufficient to sustain production and meet LBB-Kaiserslautern's new 
estimated construction completion date of January 2009. This projected 
date represents construction completion; however, the facility will not 
be open to the public for about 4 months following construction 
completion. Moreover, because LBB-Kaiserslautern has not met earlier 
construction schedules and the estimated construction completion date 
has continued to slip, we are concerned about LBB-Kaiserslautern's 
ability to manage actions needed to achieve the January 2009 estimated 
construction completion date. 

Figure 1: Comparison of the KMCC Food Court Area: 

Photographs of the food court area, May 2007 and May 2008: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

The comparison of the KMCC name-brand restaurant shows that the 
restaurant still requires painting, wiring, and other finishing work 
similar to that needed in 2007. 

Figure 2: Comparison of the KMCC Name-Brand Restaurant: 

Photographs of the KMCC Name-Brand Restaurant, May 2007 and May 2008: 

[See PDF for image] 

Source: GAO. 

[End of figure] 

In addition, major construction deficiency problems, such as the 
leaking roof and improperly installed kitchen exhaust ducts, which we 
discussed in our 2007 testimony, are just now being repaired. For 
example, contracts were recently awarded for the first two of four 
phases of repair work on the leaking roof, and most of the deficient 
ductwork has been removed. However, additional problems, such as 
several long cracks in the concrete floor of the AAFES store, have been 
identified by the Air Force since our last testimony. LBB- 
Kaiserslautern has retained an expert consultant to investigate the 
floor cracks, and the consultant's report recommends that joints be cut 
into the floor to control further cracking. The actual scope of the 
floor repair work and associated cost and schedule impacts are not 
known at this time. Figure 3 shows an example of these cracks. The pen 
in the photograph is provided for scale. 

Figure 3: Example of Floor Cracks in the KMCC: 

Photograph of floor cracks. 

[See PDF for image] 

Source: GAO. 

[End of figure] 

Final Costs of the KMCC Project Are Still Unknown: 

Because the Air Force does not track the total cost of the KMCC 
project, there are no accurate estimates of how much the total KMCC 
project will cost. Cost estimates provided by the Air Force primarily 
include core construction-related costs and do not account for millions 
of dollars in other costs related to the KMCC project. When all project-
related costs are taken into account, the total cost for the project 
will likely exceed $200 million.[Footnote 7] This figure was derived by 
consolidating numerous Air Force cost estimates captured in different 
accounts, such as military construction funds (MILCON), non- 
appropriated funds, and operations and maintenance funds. According to 
Air Force officials, approximately $121 million has been spent on core 
construction-related costs for the KMCC as of March 31, 2008. In 
addition, Air Force officials estimate that an additional $41 million 
in construction-related costs are required to complete the project. 
However, this estimate only relates to those costs that the Air Force 
tracks for reporting purposes. Not included in the Air Force's estimate 
are design costs, costs of rework to repair known construction 
deficiencies, foreign currency fluctuation costs, costs for furniture 
and equipment, some costs for secondary services[Footnote 8], and costs 
for the numerous Air Force personnel reassigned from other projects in 
order to help manage the KMCC construction project. For example, the 
Air Force cost estimate does not fully reflect the effect of the 
weakening dollar compared to the euro because payments from MILCON 
funded project components to cover losses due to foreign currency 
fluctuation are drawn from a separate account that the Air Force does 
not track as part of this project. Table 1 shows the Air Force cost 
estimate for core construction-related expenses along with additional 
costs associated with the project. As the table shows, an accurate 
estimate on the total cost of the project is not possible because of a 
number of unknown expenses, such as the Air Force's liability for 
contractor hindrance claims. 

Table 1: KMCC Estimated Project Costs: 

Cost Component (dollars in millions): Air Force estimated construction 
costs; Construction costs paid[A,B]; 
Air Force/LBB-Kaiserslautern cost estimate: $121.7. 

Cost Component (dollars in millions): Air Force estimated construction 
costs; Construction costs to complete the project [A,B]; 
Air Force/LBB-Kaiserslautern: cost estimate: $41.2. 

Cost Component (dollars in millions): Project costs not included in Air 
Force construction cost estimates; Additional roof repair costs; 
Air Force/LBB-Kaiserslautern cost estimate: $10.8. 

Cost Component (dollars in millions): Project costs not included in Air 
Force construction cost estimates; Additional kitchen duct repair 
costs; 
Air Force/LBB-Kaiserslautern cost estimate: $1.2. 

Cost Component (dollars in millions): Project costs not included in Air 
Force construction cost estimates; Secondary services; 
Air Force/LBB-Kaiserslautern cost estimate: $5.7. 

Cost Component (dollars in millions): Project costs not included in Air 
Force construction cost estimates; MILCON foreign currency fluctuation 
costs; 
Air Force/LBB-Kaiserslautern cost estimate: $8.6. 

Cost Component (dollars in millions): Project costs not included in Air 
Force construction cost estimates; Design costs[B]; 
Air Force/LBB-Kaiserslautern cost estimate: $8.4. 

Cost Component (dollars in millions): Project costs not included in Air 
Force construction cost estimates; Furniture and equipment[B]; 
Air Force/LBB-Kaiserslautern cost estimate: $16.3. 

Cost Component (dollars in millions): Total quantifiable costs; 
Air Force/LBB-Kaiserslautern cost estimate: $213.9. 

Cost Component (dollars in millions): Unquantifiable costs; Contractor 
hindrance claims; 
Air Force/LBB-Kaiserslautern: cost estimate: Unknown. 

Cost Component (dollars in millions): Unquantifiable costs; Repairs to 
cracking concrete; 
Air Force/LBB-Kaiserslautern cost estimate: Unknown. 

Cost Component (dollars in millions): Unquantifiable costs; Air Force 
staffing to manage the KMCC; 
Air Force/LBB-Kaiserslautern: cost estimate: Unknown. 

Cost Component (dollars in millions): 
Total project cost: 
Air Force/LBB-Kaiserslautern: cost estimate: Unknown. 

Source: Air Force (for all quantifiable project costs). 

[A] Construction costs include costs for construction contracts; 
certain secondary services; contingency costs; and supervision, 
inspection, and overhead provided by LBB-Kaiserslautern. 

[B] Cost component was included in original project documents submitted 
to Congress disclosing appropriated and nonappropriated funds 
estimates. 

[End of table] 

Additional clarification on selected project costs not included in the 
Air Force's construction cost estimate is provided below. 

* Construction deficiency repairs. Deficient construction has been 
identified on major building components, including the roof and kitchen 
exhaust ducts. LBB-Kaiserslautern is taking steps to contract for 
repairs to correct these deficiencies. 

- Roof damage. Significant sections of the roof require repair or 
replacement. The current plan is to complete repairs to the roof in 
four phases. The first phase of repairs is expected to cost $2.7 
million and is included in the Air Force's construction cost estimate, 
which according to the Air Force is being paid for primarily with funds 
withheld from the original roof contractor. Costs for repair phases two 
through four are estimated by the Air Force to cost about $10.8 million 
and are not included in its construction cost estimate. U.S. government 
funds remaining from the original roof contract are being used to fund 
the majority of phase one repairs; therefore, the phase one repair cost 
is reflected in the Air Force's construction cost estimate. Funds for 
repair phases two through four are initially being funded by the German 
government, and the Air Force excludes these costs in its construction 
costs to complete the project. 

- Kitchen exhaust ducts. The kitchen exhaust ducts installed in the 
KMCC do not comply with U.S. National Fire Protection Association 
standards specified by the Air Force. LBB-Kaiserslautern has completed 
the design for repairs to the exhaust ducts and is negotiating with its 
contractor a final price for their installation. The estimated 
installation cost is approximately $1.8 million. In early 2007, the Air 
Force agreed to pay for $600,000 of the rework and has included that 
amount in its construction cost estimate, but has not included the rest 
of the repair cost as part its construction cost estimate. 

* Secondary services. As the project has progressed, the Air Force has 
retained several contractor personnel to provide construction 
inspection, engineering, consulting, and other secondary services. For 
example, since January 2005 the Air Force has contracted for 
construction inspectors who are responsible for, among other things, 
ensuring that installed work meets the terms of the contract and 
checking that invoices correctly reflect the work performed. The cost 
for most of these secondary services is not included in the Air Force's 
construction cost estimate. Air Force officials indicated that some of 
the Air Force's technical consultants were also supporting other 
projects, but that the majority of their work involved support on the 
KMCC. Since the majority of work performed under these secondary 
services contracts relates to the KMCC project, we have included the 
cost of these contracts in the Air Force's estimate. 

Foreign currency fluctuation. Since the start of the project in 2003, 
the euro has appreciated 35 percent relative to the U.S. dollar. 
Because KMCC contractors are paid in euros but KMCC project funds are 
budgeted in dollars, the Air Force is susceptible to paying more when 
the dollar loses value. In addition, this risk has been magnified by 
the 2-year delay in completion of the project. Since the June 2007 
testimony alone, the euro has appreciated by 15 percent, from $1.35 to 
$1.55. As a result of the devaluation of the dollar, nonappropriated 
fund payers (AAFES and AFSVA) have paid about $31.9 million in foreign 
currency fluctuation expenses, and appropriated MILCON funds have paid 
$8.6 million since the project's inception. The Air Force includes 
nonappropriated fund foreign currency fluctuation costs in its 
construction cost estimates. However, because MILCON foreign currency 
fluctuation costs are paid from a separate account, the effect of 
foreign currency fluctuation is not reflected in the Air Force's 
construction cost estimate.[Footnote 9] Therefore we have included in 
the estimate based on the Air Force's reported numbers the actual 
foreign currency fluctuation costs paid to date associated with MILCON 
funds. In addition, the Air Force also did not include an allowance for 
future foreign currency fluctuation costs associated with MILCON 
funding. Based on the trend of the strengthening euro, these foreign 
currency fluctuation costs will only increase as MILCON expenses 
increase. Figure 4 shows the trend in the strengthening of the euro 
against the U.S. dollar over the past several years. 

Figure 4: Currency Exchange Rates for Euros since 2003: 

[See PDF for image] 

This figure is a line graph depicting the following data: 

Year: 2003, Q1; 
U.S. dollars to one euro: 1.0. 

Year: 2003, Q2; 
U.S. dollars to one euro: 1.2. 


Year: 2003, Q3; 
U.S. dollars to one euro: 1.2. 


Year: 2004, Q4; 
U.S. dollars to one euro: 1.2. 


Year: 2004, Q1; 
U.S. dollars to one euro: 1.25. 


Year: 2004, Q2; 
U.S. dollars to one euro: 1.2. 

Year: 2004, Q3; 
U.S. dollars to one euro: 1.2. 


Year: 2004, Q4; 
U.S. dollars to one euro: 1.3.

Year: 2005, Q1; 
U.S. dollars to one euro: 1.35. 


Year: 2005, Q2;
U.S. dollars to one euro: 1.3. 

Year: 2005, Q3;
U.S. dollars to one euro: 1.25. 


Year: 2005, Q4;
U.S. dollars to one euro: 1.2. 

Year: 2006; Q1; 
U.S. dollars to one euro: 1.2. 


Year: 2006; Q2;
U.S. dollars to one euro: 1.3. 

Year: 2006; Q3;
U.S. dollars to one euro: 1.3. 


Year: 2006; Q4;
U.S. dollars to one euro: 1.3

Year: 2007, Q1; 
U.S. dollars to one euro: 1.3. 


Year: 2007, Q2;
U.S. dollars to one euro: 1.35. 

Year: 2007, Q31;
U.S. dollars to one euro: 1.36. 


Year: 2007, Q4;
U.S. dollars to one euro: 1.5. 

Year: 2008, Q1; 
U.S. dollars to one euro: 1.5. 


Year: 2008, Q2; 
U.S. dollars to one euro: 1.55. 

Source: Federal Reserve. 

[End of figure] 

In addition to the estimated expenses listed above, there are still a 
number of significant costs associated with project completion that 
have not been estimated. These items include potential hindrance 
claims, repair of cracking concrete, and Air Force personnel costs for 
staff needed to manage the KMCC's construction. Depending on the 
resolution of these unknown costs, the total cost of the KMCC project 
could increase substantially before completion. 

* Hindrance claims. As a result of delays to the project, the Air Force 
expects that contractors will submit claims for additional costs 
incurred from being hindered in their performance. As of June 1, 2008, 
LBB-Kaiserslautern had forwarded change order requests for contractor 
hindrances totaling $8.2 million (5.4 million euros) to the Air Force. 
However, the Air Force has denied the requests because it contends that 
they are not substantiated. In anticipation of contractors making 
formal hindrance claims--that must meet a prescribed legal standard and 
would be adjudicated through the German courts--the Air Force has 
retained a consultant[Footnote 10] to evaluate the history of the 
project and prepare the Air Force's claims defense strategy.[Footnote 
11] At this time, the Air Force's potential exposure to claims is 
unknown. 

* Concrete cracking. Long cracks have been identified by the Air Force 
at various locations on concrete floors of the KMCC subsequent to our 
2007 site visit. A German court appointed an expert consultant to 
determine the severity of the cracks and identify their causes. The 
consultant's report, issued in March 2008, indicates that joints will 
need to be cut into the floor to keep additional cracks from occurring. 
LBB-Kaiserslautern subsequently initiated design work to detail the 
scope of the repairs. The Air Force expects that LBB-Kaiserslautern 
will award a contract for the repairs in July 2008. At this time, the 
cost of repairs is unknown. (See fig. 3 for an example of these 
cracks). 

* Air Force personnel costs for staff managing the KMCC. According to 
the Air Force, a team of 29 military, civilian, and contractor 
personnel manage the KMCC construction project. They are responsible 
for financial management, claims management, design and construction 
management, and stakeholder operations. This team comprises 6 military 
officers and enlisted personnel, 10 civil service employees, and 13 
contracted employees. The cost of the salaries and benefits for 
military and civil service employees who have been reassigned from 
other projects to assist in managing the KMCC project since its 
inception in 2003 is a real cost of the project but is not included in 
the Air Force's overall cost estimate. This cost is difficult to 
quantify because the military and civilian personnel occasionally work 
on other projects, and it is not clear how their time is apportioned 
among projects. 

Federal Republic of Germany funds. The extent to which project cost 
increases will be borne by the Air Force and its funding partners is 
unknown because of uncertainties regarding the $37.9 million (25 
million euros) committed by the German government for the project. The 
German government allocated $15.2 million (10 million euros) to pay 
contractors' invoices against change orders that had not yet been 
approved by the Air Force. According to the Air Force, only $8.6 
million (5.7 million euros) were actually expended by LBB- 
Kaiserslautern prior to the funds expiring at the end of calendar year 
2007. According to the German officials, this initial $8.6 million 
amounts to a loan, and the Air Force stated that it will reimburse this 
amount when it approves the change orders and makes payment against the 
associated invoices. The additional $22.7 million (15 million euros) 
are planned to be used by LBB-Kaiserslautern to fund contracts for 
rework items, such as roof repairs and kitchen exhaust duct 
replacement, and may also be used to settle contractor hindrance 
claims. In discussions with us, German officials characterized the 
$22.7 million (15 million euros) as a loan as well and said that they 
expected full repayment of funds. However, Air Force officials 
contended that they will only pay for valid work under the original 
KMCC contract and will not pay for rework. In light of these opposing 
views, for transparency purposes, all expenses paid from the German 
funds are incorporated into the total project cost regardless of which 
party is ultimately responsible for financing them. 

Delayed Completion Has Caused Opportunity Costs to Grow: 

As a result of the delayed KMCC project completion, AFSVA and AAFES, 
two major funding sources for the project, have experienced negative 
financial effects. Both AFSVA and AAFES invested in the project with 
the expectation of returns being generated in early 2006, the project's 
original construction completion date. However, the delayed completion 
has resulted in lost profits and in turn reduced the amount of funds 
AAFES and AFSVA can provide to military communities for morale, 
welfare, and recreation. For example, AAFES estimates that every month 
the KMCC's opening is delayed, AAFES loses approximately $500,000 in 
net profits from stores such as the base exchange and food court 
restaurants. In total, AAFES estimates it will have lost more than $14 
million in net profits by the time construction is estimated to be 
completed in January 2009. Also, the unavailability of the 350 hotel 
rooms to be completed in the KMCC Visitors Quarters results in the U.S. 
government paying more for lodging on the local economy. According to 
an Air Force estimate, on average each month that the opening of the 
hotel is delayed results in the U.S. government paying an additional 
$90,000 for off-base lodging of displaced personnel[Footnote 12] 
traveling at the government's expense. Estimated increases in off-base 
housing costs will total $2.9 million dollars if construction is 
completed in January 2009. 

Criminal and Civil Investigations Continue to Surround the KMCC and 
Other Projects: 

In our June 2007 testimony, we reported that several Air Force and LBB- 
Kaiserslautern personnel involved in management of the KMCC and other 
RMTP projects were under investigation by AFOSI and German police for a 
variety of issues, both criminal and civil. AFOSI officials stated that 
the cases have matured significantly since that time; however, formal 
indictments have not yet been made. Because the investigations are 
still active, AFOSI is limited as to the information it can disclose. 
However officials did state that investigations involve U.S. military 
and civilian employees, employees of LBB-Kaiserslautern, and KMCC trade 
contractors. These individuals are being investigated for offenses such 
as dereliction of duty and bribery. 

The Air Force Has Improved Controls over the KMCC Project: 

The Air Force has made significant improvements in its oversight and 
internal controls over the KMCC project. As stated in the June 2007 
testimony, the Air Force had failed to institute effective management 
oversight and internal controls in order to mitigate the high risk of 
the project. Specifically, the Air Force lacked standardized policies, 
did not have sufficient staffing to oversee the project, was not 
thoroughly reviewing invoices, and was approving change orders and 
payments on the project without proper documentation. In the last year, 
the Air Force created the RDO, which centralized management oversight 
of the KMCC project and brought together appropriate personnel 
specializing in financial management, claims management, design and 
construction management, and stakeholder operations. The Air Force has 
also standardized its invoice and change order review processes to 
minimize future risks of paying for unapproved work. The Air Force 
trained and appointed certifying officers and accountable officials for 
the KMCC project to ensure that personnel authorizing payments are 
aware of their fiduciary responsibilities. Finally, during 2007, senior 
officials within the Air Force engaged officials from the Department of 
State and the Federal Republic of Germany in an effort to encourage 
progress on the project. 

Establishment of the RDO and Improvements in Invoice and Change Order 
Reviews: 

In August 2007, the Air Force established the RDO to centralize control 
over all aspects of the KMCC project. According to the Air Force, the 
RDO has 29 personnel, which is a significant increase from the 8 
oversight personnel initially assigned to the KMCC project. These 29 
personnel are 6 military officers and enlisted personnel, 10 civil 
service employees,[Footnote 13] and 13 contracted employees. The RDO is 
divided into four branches: financial controls, ABG-75 administration, 
engineering, and operations/quality assurance. The Air Force also 
standardized policies and procedures for the four RDO branches, which 
are documented in an official operating instruction manual for the KMCC 
project. The documented policies were a measurable improvement from the 
one-page flowchart used during our last visit in 2007. As part of the 
establishment of the RDO, the Air Force also appointed and trained 9 
certifying officers and accountable officials. Certifying officers are 
responsible for certifying vouchers for payment. Accountable officials 
provide source information to a certifying officer to support a 
decision to certify a voucher for payment or to disburse funds. 
Appointment and training of these types of officials are key to 
ensuring that appropriate controls are in place over payments made by 
the Air Force. The RDO also includes 6 quality assurance engineers and 
technicians responsible for performing technical reviews of designs and 
conducting daily surveillance of the work site. 

Since creating the RDO, the Air Force has also improved its review 
process for invoices. During our initial visit last year, we reported 
how Air Force management instructed its staff to certify for payment 
invoices with items included in unapproved change orders and items that 
exceeded quantity limitations specified in contracts. The Air Force has 
since revised its policy and now rejects invoices for quantities in 
excess of contracted amounts and also rejects invoices with items 
included in unapproved change orders. For example, if the Air Force 
receives an invoice that contains charges for items contained in 
unapproved project change orders, the Air Force will reject the invoice 
and refuse payment until LBB-Kaiserslautern submits an invoice that 
only lists items that have been approved by the Air Force. In addition, 
the Air Force has gone back on prior invoices and recouped amounts 
previously paid in excess of contracted quantities. 

Involvement of Senior Air Force Officials: 

Beyond improvements over internal controls and the establishment of the 
RDO, senior Air Force, Department of State, and German government 
officials have also increased oversight of the project. Beginning in 
August 2007, the U.S. Air Forces in Europe Vice Commander, the U.S. 
Ambassador to Germany, and the heads of the German Ministry of 
Construction and the German Ministry of Finance started meeting 
regularly to discuss problems facing the KMCC. These repeated meetings 
between U.S. and German officials prompted the German government to 
provide $37.9 million (25 million euros) to the project for backlogged 
change orders and repair work. According to the Air Force, German 
support is essential for a successful completion of the KMCC project. 
The Air Force's expectation is that by maintaining strong relationships 
among senior officials, it will ensure that those running the KMCC 
project are able to better organize, prioritize, and execute the 
project. Unfortunately, this joint effort has not yet expedited KMCC 
construction to an acceptable pace according to Air Force officials. 

Other Recent U.S. Projects on Ramstein Air Base Have Experienced 
Similar Problems: 

Other projects recently completed in the KMCC area managed by LBB- 
Kaiserslautern have experienced problems similar to those affecting the 
KMCC. Air Force officials report that several recent projects on 
Ramstein Air Base experienced cost and schedule growth, including 
projects that were delivered by LBB-Kaiserslautern months after the 
planned delivery dates. In addition, several projects were delivered 
with construction flaws that have caused flights to be diverted and 
have affected the processing of freight shipments. According to the Air 
Force, it has experienced fewer problems with less sophisticated 
projects, such as the construction of more than 1,000 new military 
family housing units in the KMCC area and the construction of an indoor 
pool on Ramstein Air Base, that were managed by LBB-Kaiserslautern. 
However, construction of these projects is not comparable to the scope 
and complexity of constructing the KMCC building, runways, and other 
operational facilities. 

Cost and Schedule Growth of Other Projects: 

Numerous recent projects associated with the RMTP built on Ramstein Air 
Base by LBB-Kaiserslautern have experienced significant cost growth, 
according to the Air Force. Several of these projects have also not 
received final bills from LBB-Kaiserslautern despite being turned over 
to the United States more than a year ago. Therefore, the final costs 
of the projects are still unknown. In addition, many of the same group 
of projects managed by LBB-Kaiserslautern also experienced significant 
schedule growth according to the Air Force, including projects that 
were delivered months after their scheduled completion dates. 

Construction Deficiencies of Other Recently Completed Projects: 

Construction deficiencies experienced on several of the RMTP projects 
built by LBB-Kaiserslautern add to the concerns associated with cost 
and schedule growth. Specifically, there have been several projects 
where faulty construction has resulted in safety concerns, building 
evacuations, and potentially reduced useful lives of facilities. Below 
are examples of such problems. 

* South runway. This runway was recently built on Ramstein Air Base in 
order to upgrade the base's capabilities in support of overseas 
missions, including those in Iraq and Afghanistan. However, the runway 
lights are adversely affected by a construction defect that allows 
groundwater to collect in the underground ducts and manholes that 
contain electrical components used to control the lights. The intrusion 
of water has damaged electrical components resulting in power outages 
to the lights. These lights are crucial for operations because they 
allow aircraft to land during times of extremely limited visibility. 
According to the Air Force, because of the lighting failures, aircraft 
could not land during periods of limited visibility from November 
through December 2007 and flights were diverted to other bases in 
Europe. Portable lights have been used to temporarily resolve the 
problem. Additionally, water is pumped from the manholes as an ongoing 
maintenance activity that according to Air Force officials, has cost 
about $65,000 to date. Finally, during rainy periods, several large 
ponds developed between the south runway and adjacent runways and 
taxiways because of poor water drainage. These ponds, which were 
several acres in total area during our visit in March 2008, have 
attracted large waterfowl, which pose a safety hazard to aircraft using 
the runway. Figure 5 shows one of these large ponds. Studies and court 
actions are currently under way to resolve these issues. 

Figure 5: Example of Large Pond Next to Ramstein's South Runway: 

{See PDF for image] 

Photograph of large pond next to Ramstein's South Runway. 

Source: GAO. 

[End of figure] 

* Freight terminal. This large 100,000 square foot material handling 
facility was constructed to assist in processing freight shipments to 
and from overseas locations. However, deficiencies with the structural 
steel that frames the freight terminal required evacuation of the 
building until additional support columns could be installed. According 
to the Air Force, because of material fabrication issues, insufficient 
welds, and undersized connections, the steel structure that supports 
the freight terminal building was determined to be at risk of 
collapsing. As an interim safety measure, 41 additional support columns 
were installed to bolster the structural integrity of the facility. 
According to the Air Force, these additional supports effectively 
reduce the open area in the center of the facility and affect freight 
processing operations. For example, forklifts are restricted in 
maneuvering and cannot access certain areas. Figure 6 shows an example 
of the additional support columns installed within the freight terminal 
building. A permanent resolution will be determined by legal 
proceedings that are currently ongoing in the German courts. In 
addition, officials were concerned that a building attached to the 
freight terminal was also structurally deficient as a result of 
potentially insufficient welds on the structural steel. Because of 
these concerns, the building was evacuated from July through September 
2007 while additional support columns were installed. An inspection 
completed in March 2008 confirmed that the structural steel was, in 
fact, installed correctly and that the building is not at risk of 
collapsing. The attached building is currently being used as intended. 

Figure 6: Example of Additional Support Column Installed in the Freight 
Terminal: 

[See PDF for image] 

Photograph of additional support column installed in the Freight 
Terminal. 

Source: GAO. 

[End of figure] 

* Hot cargo pad. A large concrete area intended to be used for loading 
live munitions onto aircraft destined for overseas locations such as 
Iraq and Afghanistan was recently built near the Ramstein Air Base 
runway. However, when building the concrete pad, contractors did not 
install dowels between adjacent concrete slabs as is typically done in 
this type of construction. Because the dowels were not installed, Air 
Force officials stated that differential settling of the concrete slabs 
could result in damage to the cargo pad and reduce its useful life. The 
Air Force is currently negotiating with LBB-Kaiserslautern to determine 
what, if any, actions will be taken to address this issue. While this 
does not represent a safety risk, the reduced life span of the cargo 
pad could result in the Air Force spending money for repair or 
replacement earlier than would normally be expected. 

Concluding Comments: 

Although the Air Force has made measurable improvements in its 
oversight and control of the KMCC since our last testimony, the project 
remains at risk because of schedule and cost uncertainties. With few 
visible changes, no reliable construction completion date, rising 
repair costs, and continuing construction quality problems, the KMCC 
will continue to be a high-risk project. Even after the KMCC is 
completed and open, it will likely take years before all issues related 
to this project, including litigation and potential construction 
quality problems, are resolved. 

Mr. Chairman and Members of the Committee, this concludes our 
statement. We would be pleased to answer any questions that you or 
other members of the committee may have at this time. 

GAO Contacts: 

For further information about this testimony, please contact Gregory 
Kutz at (202) 512-6722 or [email protected] or Terrell Dorn at (202) 512- 
6293 or [email protected]. Contact points for our Offices of Congressional 
Relations and Public Affairs may be found on the last page of this 
testimony. 

[End of section] 

Appendix I: Scope and Methodology: 

To determine the current status of the Kaiserslautern Military 
Community Center (KMCC) construction project, including projected 
costs, cost completion analyses, projected construction completion 
dates, and status of ongoing investigations, we interviewed officials 
from the Air Force at Ramstein Air Base in Germany, the Army and Air 
Force Exchange Service (AAFES), the Air Force Services Agency (AFSVA), 
the U.S. Army Corps of Engineers (USACE), the Air Force Audit Agency, 
the Air Force Office of Special Investigations (AFOSI), and the 
Department of State. In addition, we interviewed officials from 
Landesbetrieb Liegenschafts-und Baubetreuung office in Kaiserslautern 
(LBB-Kaiserslautern), the German government construction agency; the 
Federal Republic of Germany's construction division; and the German 
police. We physically inspected the KMCC facility with an Air Force 
project manager and observed construction deficiencies. We also 
reviewed financial records and statements in the form of contracts, 
change orders, and invoices to the extent that they were available. We 
also compiled Air Force and LBB-Kaiserslautern cost estimates for the 
various cost elements associated with the KMCC project. 

To determine whether oversight and internal control improvements have 
been made by the Air Force since our last testimony, we interviewed Air 
Force officials from the KMCC Resident Director's Office. We also 
interviewed officials from LBB-Kaiserslautern, AAFES, AFSVA, AFOSI and 
the Air Force Audit Agency. We obtained and reviewed project management 
plans, standardized policies and procedures, cost estimates, training 
materials for certifying officers and accountable officials, and other 
relevant documents related to project management. 

To determine if other projects recently completed in the KMCC area have 
experienced problems similar to those affecting the KMCC, we 
interviewed Air Force officials regarding their construction projects 
in Germany. We also conducted interviews with other organizations, 
including USACE, AFOSI, LBB-Kaiserslautern, and the Air Force Center 
for Engineering and the Environment to understand the cost, schedule, 
and construction flaws experienced by other military construction 
projects in the KMCC area and how they may affect the viability of 
future construction projects. We also reviewed available technical 
expert reports documenting construction deficiencies associated with 
these projects. 

Because of ongoing investigations, we were not able to fully explore 
and discuss the details of fraud investigations with AFOSI and the 
German police, which limited the scope of our audit. 

We conducted this performance audit from November 2007 through June 
2008 in accordance with generally accepted government auditing 
standards. Those standards require that we plan and perform the audit 
to obtain sufficient, appropriate evidence to provide a reasonable 
basis for our findings and conclusions based on our audit objectives. 
We believe that the evidence obtained provides a reasonable basis for 
our findings and conclusions based on our audit objectives. 

[End of testimony] 

Footnotes: 

[1] GAO, Military Construction: Observations on Mismanagement of the 
Kaiserslautern Military Community Center, [hyperlink, 
http://www.gao.gov/cgi-bin/getrpt?GAO-07-1039T] (Washington, D.C.: June 
28, 2007). 

[2] AAFES is a joint military activity providing merchandise and 
services to active duty, guard and reserve members, military retirees, 
and their families. AAFES uses earnings to improve troops' quality of 
life and to support morale, welfare, and recreation programs. AFSVA 
provides combat support and community service programs that enhance the 
quality of life for Air Force members and their families. AFSVA 
programs include lodging, youth programs, and sports and fitness 
programs. 

[3] The closure of the Rhein Main Air Base is part of the RMTP where 
the United States and Germany agreed to return the base to Germany. In 
return, Germany allowed the relocation of the base's key airlift 
capability to Ramstein and Spangdahlem Air Bases. As part of the 
agreement, the Federal Republic of Germany, federal states of Rheinland-
Palatinate and Hessen, city of Frankfurt, and Fraport AG Frankfurt 
Airport Services Worldwide agreed to provide funds to upgrade the 
facilities at Ramstein and Spangdahlem Air Bases, including about 14 
million euros for the KMCC. 

[4] For all contract and cost amounts accounted for in euros, we 
converted costs into U.S. dollars at the specific conversion rate 
estimated by Air Force officials for that specific cost element. In 
cases where the Air Force did not have a specific conversion rate set 
for a cost element, we converted the cost at a rate of .66 euros per 
dollar, which was the most recent conversion rate used by the Air Force 
for planning purposes. 

[5] Hindrance claims refer to claims against the United States for 
additional costs contractors incurred because of interruptions of 
contractor work. 

[6] The German government has loaned the project 25 million euros since 
our 2007 testimony to finance rework and repairs, prepay invoices, and 
settle contractor hindrance claims. German officials stated to us that 
complete reimbursement for this loan from the United States is 
expected. However, the Air Force contends that it will not pay for any 
expenses related to rework or repairs to deficient construction. For 
transparency purposes, we consider that all expenses funded by proceeds 
from the loan are part of the total project cost regardless of which 
party is ultimately responsible for financing each specific cost. 

[7] Estimates for each independent cost element were developed by the 
Air Force and German government officials; however, our review of these 
estimates in aggregate resulted in confidence that the overall project 
cost will likely exceed $200 million. 

[8] Secondary services, also called soft costs, include work performed 
by construction inspectors who are responsible for ensuring that 
installed work meets the terms of the contract and checking that 
invoices correctly reflect the work performed. Secondary services also 
include consulting and logistical support services. 

[9] Costs associated with foreign currency fluctuation for appropriated 
MILCON funds are paid from a central MILCON foreign currency 
fluctuation account and are not charged directly to projects. 

[10] The cost of this claims consultant is included in the secondary 
services cost estimate. 

[11] The consultant is also investigating if there are areas where the 
Air Force may be able to recover costs for problems caused by designer 
or contractor errors. 

[12] Displaced personnel include military and civilian personnel in 
temporary duty status from the Air Force and other agencies, as well as 
contractors who are eligible for military lodging. 

[13] As previously discussed, salary and benefit costs for the military 
and civil service employees are not included in the overall project 
costs. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: [email protected]: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, [email protected]: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, [email protected]: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: 

*** End of document. ***