06-1433 - Abramo et al v. Shaw


Download Files

Metadata

Document in Context
06-1433 - Abramo et al v. Shaw
January 14, 2008
PDF | More
DECISION AND ORDER granting 11 Motion for Summary Judgment. ORDERED that Plaintiff's Motion for Summary Judgment is GRANTED. ORDERED that Plaintiff's are entitled the sum of $100,000.00, plus interest at the rate of 9% annum, an award of specific performance obligating defendant to fulfill his obligations under section 4.2 (c) of the agreement, including posting $1,652,962 collateral with the surety, and any additional amounts the surety may require in connection with construction jobs existing at the time the parties entered into the Agreement, and an award of reasonable attorney's fees, costs, and disbursements incurred as a result of the breach. Signed by Judge Lawrence E. Kahn on 1/14/08. (ban)